The Chancellor commented on the following summary of the cost of constructing Thomas Jefferson Hall:
Construction | ||
Thorington Construction Company | ||
Base Bid | $ 865,440 | |
Alternate A | $ 82,000 | |
Alternate G | 25,500 | |
Alternate H | 6,700 | 114,200 |
$ 979,640 | ||
Alternate E | 7,400 | |
$ 972,240 | ||
Change Order No. 1 | 8,100 | |
Total | $ 980,340 | |
Equipment | ||
Thalhimer Brothers | $ 55,649 | |
Alternate No. 1 | 5,353 | |
Alternate No. 2 | 1,287 | |
$ 62,289 | ||
Change Order No. 1 | 4,080 | |
$ 66,369 | ||
Other Equipment | 75,000 | $ 141,369 |
Architects Fees | ||||
Construction | 5.5% | $ 980,340 | $ 53,919 | |
Equipment | 7.64% | 66,369 | 5,070 | $ 58,989 |
Contingencies | 20,812 | |||
----------- | ||||
Total | $ 1,201,510 | |||
Available Funds | ||||
Proceeds of Bond Issue | $ 815,000 | |||
Temporary Loan | 300,000 | |||
State - site improvements | $ 82,000 | |||
5.5% 82,000 | 4,510 | 86,510 | ||
$1,201,510 |