THOMAS JEFFERSON HALL
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

THOMAS JEFFERSON HALL

The Chancellor commented on the following summary of the cost of constructing Thomas Jefferson Hall:

Thomas Jefferson Hall

                   
Construction 
Thorington Construction Company 
Base Bid  $ 865,440 
Alternate A  $ 82,000 
Alternate G  25,500 
Alternate H  6,700  114,200 
$ 979,640 
Alternate E  7,400 
$ 972,240 
Change Order No. 1  8,100 
Total  $ 980,340 
Equipment 
Thalhimer Brothers  $ 55,649 
Alternate No. 1  5,353 
Alternate No. 2  1,287 
$ 62,289 
Change Order No. 1  4,080 
$ 66,369 
Other Equipment  75,000  $ 141,369 
            
Architects Fees 
Construction  5.5%  $ 980,340  $ 53,919 
Equipment  7.64%  66,369  5,070  $ 58,989 
Contingencies  20,812 
----------- 
Total  $ 1,201,510 
Available Funds 
Proceeds of Bond Issue  $ 815,000 
Temporary Loan  300,000 
State - site improvements  $ 82,000 
5.5% 82,000  4,510  86,510 
$1,201,510