3. PROJECTED COSTS OF EXTENDED PROJECT MANAGEMENT CONSULTING SERVICES
 
 
 



3. PROJECTED COSTS OF EXTENDED PROJECT MANAGEMENT
CONSULTING SERVICES

It is agreed that extended on-site project management consulting staff, together with related off-site support services, will be provided in accordance with the following summary, and their costs shall be limited to the budget amount shown unless these amounts are increased by prior written agreement between the University and Bechtel. Any such increase will be considered an amendment to the contract, and shall be covered by Section 7 of Attachment B, Mandatory Contractual Provisions of the University's Request for Proposal No. 8350 of July 20, 1984.

A. General Project Management Consulting Services

Extended on-site project management consulting services will be provided by Bechtel for the duration of construction of vertical and horizontal expansion of the Replacement Hospital and renovations of the Multi-story Hospital which are scheduled to end at the beginning of 1990.

For these extended project management consulting services, Bechtel shall provide full-time on-site project management staffing as follows:

   
Project Manager  -October 1988 to December 1988 
Project Manager, Construction  -October 1988 to April 1990 
Construction Engineer Multi-story Hospital  -March 1988 to February 1990 

Estimated total is 46 man-months. In addition, the services of the Project Manager, Resident Manager-Construction, and Expediter presently provided for the current contract will be extended through September 1988 under same terms as Amendment No. 1.

B. Special Project Management Consulting Services

Special services from the Bechtel home office shall be provided during the extended period of project management consulting services in accordance with the terms and conditions of Amendment No. 1. These services shall be provided upon the request of the on-site project manager.



C. Budget for Additional Project Management
Consulting Services

It is agreed that the additional services provided by Bechtel shall be limited to the amounts budgeted, as summarized below, unless these amounts are increased by prior written agreement by the University.

    
On-site services  $620,000 
Off-site services  $250,000 
Total  $870,000 
Optional GMP check estimate - $28,000 



Witness the following signatures as of this ____ day of ____, 1988.