University of Virginia Library

Search this document 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
collapse section
 
 
 
collapse section
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
collapse section
 
 
 
 
 
collapse section
collapse section
 
 
collapse section
 
A. Direct and Indirect Costs
collapse section
 
 
 

A. Direct and Indirect Costs

Paragraph A(3)(a) and (b) of Amendment No. 1 are hereby amended to read as follows:



                  
Grade  Position  Current Rates (1987) ($/day)  1988 Rates ($/day) 
(a) Off-site  (home office assignments, technical)  [14]  
30  Project Sponsor, Manager of Projects  905 
29  Senior Project Manager, Chief Engineer  846 
28  Project Manager; Engineering Supervisor  752 
27  Assistant Project Manager, Project Operations Specialist; Technical Specialist  670 
26  Technical or Operations Specialist; Project Administrator  575 
25  Project Construction Coordinator; Administrative Specialist  481 
24  Construction Engineer; Administrative Assistant  422 
23  Administrative Assistant; Technologist  364 
22  Administrative Assistant  317 
(b) On-site (permanent assignments) 
29  Resident Manager  717 
28  Resident Manager (construction)  646 
27  Assistant Resident Manager  564 
26  Senior Construction Engineer; Contract Engineer  494 
25  Construction Engineer; Contract Engineer  414 
24  Expeditor  364 

These daily rates are based on a 40-hour work week, 5 days per week. Daily rates include payroll costs for secretarial and other non-technical staff supporting project-related activities at the home offices. The rates are a weighted average and are subject to adjustment as mandated by Bechtel's personnel policies and practices. Off-site positions shown in the above are for typical potential assignments. They may vary with project requirements. Billing will be on a time card basis for a given salary grade. Daily rates will be prorated if less than 8 hours-per-day are worked off-site. Travel time will be billed when traveling on project business.

 
[14]

Actual rates for 1988 and thereafter will be determined under procedure used for 1987 and 1986/85.