Estimate of the Cost of the Rotunda

An Estimate of the cost of the Rotunda as far as the contracts that have been made towards
the completion of it go--

                             
Amt. Paid for Materials for the brick work  $6,905.47 
Amt. pd to Thorn & Chamberlain for the work  2,856.25 
9,761.72 
Amt. To complete the brick work of the Lbrary
& Terras say  
1,000.00 
Amt. Contract with G. Raggi for 10 Bases
& 2 Pilaster bases[869]  
715.00 
Cost of Capitels in Italy say  7,000.00 
Transportation, duty &c on the Same & bases  2,450.00 
10,165.00 
pd for Stone Window & doorsills  255.00 
to complete the stone steps on the back & Terras
Stonework  
1,200.00 
1,455.00 
paid for Materials principally Lumber & iron
which nearly pays for all the Lumber  
6,165.00 
For Tin & Copper for the roof of Dome & Portico  2,000.00 
Glass & Glazing including the sky light  500.00 
$31,046.72 

Nails, hard ware, painting & Workmans bills will not
I presume exceed the balance of the $41,000

respectfully submited by your obt sert A. S Brockenbrough P.

ADS, ViU:PP, 1p [2066] with TJ docket "Rotunda. A. S. Brockenbro's estimate"; printed,
O'Neal, Jefferson's Buildings at the University of Virginia: The Rotunda, 30. This document
is badly stained.

 
[869]

869. For the university's contract for these bases, see TJ to Brockenbrough, 2 September
1823, and Raggi and Brockenbrough's Agreement, 8 September 1823.