REPORT ON CONSTRUCTION
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

REPORT ON CONSTRUCTION

Vice-President Catlin distributed a report on the status of construction projects at the University. The report indicated a February 20, 1976 completion date for the restoration of the Rotunda. The largest project mentioned is the Primary Care Center with a projected cost of $11,578,295.