III. Scope of Policy
                     The current pre-planning process and budget development process for capital
                        projects has not been altered by the enabling legislation. Consequently,
                        this policy statement will only apply to post-appropriation implementation
                        of capital projects which are funded 
 entirely or in part by a
                        state general fund, state supported debt, or non-general fund appropriation
                        made by the General Assembly. Specifically, this policy applies to items
                        identified as authorized capital projects for the University of Virginia or
                        the University of Virginia Medical Center in an Appropriation Act enacted by
                        the General Assembly and approved by the Governor. For non- Medical Center
                        projects at the University, this policy is applicable only during the
                        1996-1998 biennium unless extended or continued by a subsequent act of the
                        General Assembly. In accordance with the 2003 Appropriations Act new
                        construction projects costing less than $750,000 and non-general fund
                        renovation projects costing less than $1,000,000 are exempt from this
                        policy, except that the provisions of Section IX shall apply to any project
                        costing in excess of $100,000. The terms and structure of any financing of
                        any capital project shall remain subject to other provisions of law
                        including, but not limited to, § 2.2-2416 of the Code of Virginia.