Hospital.

The appropriation of $31,000. received from the State,
from special appropriation by the Legislature, has been expended
in the erection of a new wing to the Hospital. There
has also been expended an additional sum of $2,800. appropriated
from the current Receipts of the University. The
Chairman of the Building Committee reports that there is still
due to the Contractors and Architects a balance of $2,203.25,
for payment of which some provision should be made by the
Board.

It is hoped at the coming session of the Legislature to
get the $35,000 for the other wing of the Hospital, which will
complete the whole as originally designed, and will give us a
central Hospital of such proportions as will supply the needs
of this University, and of this whole section of country.