University of Virginia Library

Search this document 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
REPORT ON CONSTRUCTION
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
expand section
 
expand section

REPORT ON CONSTRUCTION

The President reported that there is extensive construction activity in all divisions of the University. He said that work is proceeding on schedule for the Replacement Hospital. The expected completion date of the project is July 1988.

The total cost of construction projects in the Medical Center is $238,942,821, while those in the University Division total $69,880,163. Projects at Clinch Valley College total $535,000.