PHASE V: CONSTRUCTION
-Set slope and grade stakes; clear and grub site - grading
and excavation - demolition of structures-Stake-out centerline and subgrade stakes - install drainage
structures and lighting-Grade ditches and final grading of slopes
-Lay down subbase material - grade shoulders
-Install curbs - rake to subgrade, spread topsoil, seed
and plant-Lay down base course - lay down surface course, stall lighting,
erect roadside signs-Hold pre-final inspection - write up punchlist - final finishing