University of Virginia Library

Search this document 
 
 
 

collapse section
collapse section
 
 
 
 
 
collapse section
 
 
 
collapse section
 
 
collapse section
 
 
 
collapse section
 
collapse section
 
 
 
 
 
collapse section
 
 
 
 
 
 
 
 
 
 
 
 
 
 
collapse section
 
 
 
 
 
collapse section
 
 
 
 
 
 
collapse section
 
 
 
 
 
 
collapse section
 
collapse section
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
collapse section
collapse section
THE SEQUENCE OF ROAD CONSTRUCTION
 
 
 
 
 
 
 
collapse section
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

collapse section
 
 

3

Page 3

THE SEQUENCE OF ROAD CONSTRUCTION

Note: Public hearings are required to be conducted by the States
for funding under Federal Aid for Highways.

PHASE I: PRE-PLANNING

  • -Establish need through highway system plan; conduct origin
    and destination studies.

  • -Establish purpose - primary, secondary, urban

  • -Establish criteria - design speed, gradient, access, capacity, et

  • -Establish route - examine land ownerships, costs of R.O.W.,
    aerial surveys

  • -Conduct public hearings - submit report of hearings to FHWA

  • -Draft EIS or negative declaration - project is or is not
    major action.

PHASE II: PRELIMINARY PLANNING

  • -Prepare location studies

  • -Flag "P Line" with Team - engineer, biologist, manager

  • -Conduct route survey

  • -Prepare alignment studies - notify other authorities of proposal
    - submit draft of EIS to other agencies

  • -Conduct public hearings - submit report of hearings to FHWA

  • - Receive final approval of PS&E and authorization of funds

PHASE III: PROJECT PLANNING OR PS&E (Plans, specs & estimates)

  • -Note: FHWA calls phase "Plans, Surveys & Engineering"

  • -Prepare construction drawings, specifications and final estimates

  • -Conduct field review (plans in hand) with FHWA representative

  • -Receive final approval of PS&E and authorization of funds

PHASE IV: BIDS AND PRE-CONTRACT

  • -Send notices of intent to advertise to journals, CBD (Commerce
    Business Daily), newspapers, etc. - request wage rates

  • -Advertise - mail plans and specs to prospective bidders

  • -Open bids - examine prices, bid bond, reputation of bidders, etc.

  • -Award contract to successful bidder - Contracting Officer
    signs contract - hold pre-construction conference

  • -Issue Notice to Proceed.

PHASE V: CONSTRUCTION

  • -Set slope and grade stakes; clear and grub site - grading
    and excavation - demolition of structures

  • -Stake-out centerline and subgrade stakes - install drainage
    structures and lighting


  • 4

    Page 4
  • -Grade ditches and final grading of slopes

  • -Lay down subbase material - grade shoulders

  • -Install curbs - rake to subgrade, spread topsoil, seed
    and plant

  • -Lay down base course - lay down surface course, stall lighting,
    erect roadside signs

  • -Hold pre-final inspection - write up punchlist - final finishing

PHASE VI: FINAL INSPECTION

  • -Walk job with FHWA representative, the contractor, his superintendent,
    the inspector or project supervisor may be yourself,
    and the maintenance supervisor

  • -Inspect job to see that all items on punchlist are corrected
    and the work is completed

  • -Check all quantities by measurement and recommend for payment -
    settle all possible disputes or reasons for later claims

  • -Notify contractor of acceptance

PHASE VII: FINAL PAYMENT AND COMPLETION REPORT

  • -Recommend final payment by agency or owner - submit as-builts
    (drawings) and completion report for record of work

  • -Note: Job log is not part of contract documents but may be
    used as evidence in court.


5

Page 5
illustration

6

Page 6
illustration