APPROVAL OF PROJECT BUDGET INCREASES IN EXCESS OF 10 PERCENT AND PROJECT SCOPE DECREASE IN EXCESS OF 10 PERCENT
 
 
 
 
 
 
 
 
 
expand section
 
 
 
expand section
 
expand section
expand section
 
expand section
expand section
expand section
 
expand section
expand section
expand section
expand section

APPROVAL OF PROJECT BUDGET INCREASES IN EXCESS OF 10 PERCENT AND PROJECT SCOPE DECREASE IN EXCESS OF 10 PERCENT

(approved by the Buildings and Grounds Committee on January 22, 2007)

RESOLVED that the project budget increases for the Advanced Research and Technology Building (to $45.4 million), Bavaro Hall (to $37.2 million), the Upgrade of Jordan Hall HVAC Systems (to $28.9 million) and the project scope decrease for Bavaro Hall (to 68,800 gross square foot) are approved.