University of Virginia Library

Search this document 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
expand section
 
 
 
 
 
 
 
 
 
 
APPROVAL OF CHANGE IN PROCEDURE FOR THE SELECTION OF ARCHITECTS
 
 
 
 
 
 
 
 

APPROVAL OF CHANGE IN PROCEDURE FOR THE SELECTION OF ARCHITECTS

The following resolution was adopted:

  • RESOLVED that the following revised procedures for the selection and approval of architects and engineers for Capital Outlay projects be and they are hereby approved as follows:
  • 1. Selection of architects and engineers for Capital Outlay projects shall be submitted for the approval of the Board for all projects meeting the following criteria:
  • a. Any commission or contract for the design of new facilities, additions to existing facilities, or renovations affecting the exterior appearance of existing facilities, regardless of total project cost.
  • b. Any commission or contract for the design of improvements or renovations at a total project cost of $500,000 or more.
  • c. Any commission or contract to an out-of-state firm for either preplanning studies or design services.

  • 2400

  • 2. Selection of architects and engineers for Capital Outlay projects may be approved by the University administration (with prior notification to the Chairman of the Buildings and Grounds Committee) and the Board advised, for projects as follows:
  • a. All preplanning studies not involving out-of-state firms.
  • b. Any commission or contract for the design of improvements or renovations at a total project cost of less than $500,000, not involving out-of-state firms.