University of Virginia Library

Search this document 

 
 
 
 
 
 
expand section
 
expand section
expand section
 
 
 
expand section
expand section
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
APPROVAL OF PROJECT SCOPE, BUDGET MODIFICATIONS, AND ADDITIONAL USE OF DEBT
expand section
 
 
 
 
 
 
 
expand section
collapse section
 
 
 
 
 
 
expand section
expand section
expand section
expand section


7334

APPROVAL OF PROJECT SCOPE, BUDGET MODIFICATIONS, AND ADDITIONAL USE OF DEBT

(approved by the Finance Committee on June 7, 2007)

RESOLVED that the $3.305 million budget increase and use of additional University debt for the Emily C. Couric Clinical Cancer Center (bringing the total budget to $74.0 million); the $2.2 million budget increase and use of additional University debt for the Hospital Bed Expansion Project (bringing the total budget to $80.178 million); and the $2.15 million budget increase for the renovation of Crockett Hall at The University of Virginia College at Wise (bringing the total budget to $6.9 million) are approved.