APPROVAL OF PROJECT SCOPE, BUDGET MODIFICATIONS, AND ADDITIONAL USE OF DEBT

(approved by the Finance Committee on June 7, 2007)

RESOLVED that the $3.305 million budget increase and use of additional University debt for the Emily C. Couric Clinical Cancer Center (bringing the total budget to $74.0 million); the $2.2 million budget increase and use of additional University debt for the Hospital Bed Expansion Project (bringing the total budget to $80.178 million); and the $2.15 million budget increase for the renovation of Crockett Hall at The University of Virginia College at Wise (bringing the total budget to $6.9 million) are approved.