Board of Visitors minutes October 5, 1990 | ||
0003
renumbered, no b. in August 13 draft
- b. The Foundation shall complete the purchase of the Hillcrest site by November 1, 1990, and will secure a firm commitment from the present owner that construction of the required access road will begin within 45 days of the availability of construction documents, and will be completed within 6 months of the availability of documents.
- In completing the purchase of the Hillcrest site the Real Estate Foundation will obtain a commitment from the seller that construction of the required access road will commence within 45 days following the required approvals of construction documents by the authorities having approval authority, and will be completed within months of recept of the complete construction documents or , 1991, whichever date occurs first.
- c. The University will assume full responsibility for any construction costs for off site access roads, and off-site water and sewer above a $610,000 commitment for this work on the part of the original land owner.
- d. TheSubject to the conditions in the next two
sentences, the University agrees that it will
permit Forestry continued use of existing warehouse
facilities on Forestry's 32 acre site south of
Charlottesville until completion and occupancy of
the new headquarters building and administrative
support facility. Pending completion of the new
facilities, this use may continue for up to five
years from the date of transfer of the property.
Continued use of the facilities beyond the five
year period, if Forestry's new facilities have not
been completed, will be the subject of future negotiations.0004
- 2. The University agrees to provide financial support to Forestry for construction costs of the headquarters office building and administrative support facility as follows:
- a. A ixed amount of $1.1 million will be provided to compensate for additional site development costs required by the change from the original project site to the Hillcrest site, and inflation in the building tion resulting from a delay of approximately fifteen months in completion of contract documents for the work as a result of the changed site. This amount represents the full and only commitment of the University to increased construction costs for the project resulting from the change in site.
- b. The University will make an additional payment of $1.4 million reflecting the balance of a commitment to purchase the existing Forestry site south of Charlottesville for $1.5 million.
- c. The $3.5 million total of the foregoing commitments will be transferred by the University to Forestry at the time bids are received and a construction contract awarded in the Fall of 1990.
- d. If contract bidding and an award of a construction
contract are delayed for any reason, the University
will deposit the total commitment of $2.5 million
into an escrow account no later than October 15,
1990.This escrow amount, and any accrued
intoroct will be everting and available
solely to Forestry to be used for construction of
the headquarters office building and administrative
support facility should the project proceed at any
time during a five year-period following October
15, 1990.It is the intent of the parties, in setting up the escrow account, that principal and interest be dedicated to and expended solely for construction of the Department of Forestry's new headquarters office building and administrative support facility at the Hillcrest site, should that project proceed at any time during a five-year period commencing October 15, 1990.If, after five years of establishment of the escrow account, the project has not proceeded into construction, the escrowed amount and all accrued interests will revert to the University. If construction has not commenced at the Hillcrest site before October 14, 1995, then the escrowed amount together with all accrued interest will revert to the University.0005
- 3. Forestry agrees that it will utilize the land and financial resources provided by the University for the purpose of constructing the headquarters office building and administive support facility, and that upon completion of these facilities, all existing facilities and property adjacent to Alderman and McCormick Roads on the grounds of the University will be relinquished to the University without additional compensation. If for whatever reason, Forestry is unable to construct and/or occupy a new headquarters office complex, it is understood that Forestry will remain at its present location. White Note: This change "is unacceptable to the University. The University that this ement contain uarante with respect to the on-Grounds building now occupied by Forestry beyond the five-year period referenced in Paragraph 2.d.
- 4. In order to provide an alternate procedure for development
of the required facilities for Forestry, should the required
general fund commitment from the Commonwealth not become
available in a timely manner, the parties to this Agreement
further agree that they will develop a plan under which the
required facilities could be developed by the Foundation and made under a l .0006
- 5. This plan supporting data and required documents will be developed and finalized by December 1, 1000 to be prepared for the 1991 Session of the General Assembly of Virginia.
J. W. Garner, State Forester Department of Forestry
Date
Leonard W. Sandridge, Jr.
Senior Vice President and Chief Financial Officer University of Virginia
Date
David-Westy Executive Director University of Virginia Real Estate Foundation
Date
3:93/795M
Board of Visitors minutes October 5, 1990 | ||