REPORT ON CONSTRUCTION
The President reported that for the University Division construction projects are valued at $57,926,181; for the Medical Center $252,216,612, and for Clinch Valley College $1,577,145. The largest project is the Replacement Hospital and site preparation with a budget of $199,170,000. All elements of the hospital building are complete. The Replacement Hospital completion date is September 1988, and the expanded Replacement Hospital is due to open in January of 1990.