| Board of Visitors minutes October 7, 1966 | ||
THOMAS JEFFERSON HALL
The Chancellor commented on the following summary of the cost of constructing Thomas Jefferson Hall:
| Construction | ||
| Thorington Construction Company | ||
| Base Bid | $ 865,440 | |
| Alternate A | $ 82,000 | |
| Alternate G | 25,500 | |
| Alternate H | 6,700 | 114,200 |
| $ 979,640 | ||
| Alternate E | 7,400 | |
| $ 972,240 | ||
| Change Order No. 1 | 8,100 | |
| Total | $ 980,340 | |
| Equipment | ||
| Thalhimer Brothers | $ 55,649 | |
| Alternate No. 1 | 5,353 | |
| Alternate No. 2 | 1,287 | |
| $ 62,289 | ||
| Change Order No. 1 | 4,080 | |
| $ 66,369 | ||
| Other Equipment | 75,000 | $ 141,369 |
| Architects Fees | ||||
| Construction | 5.5% | $ 980,340 | $ 53,919 | |
| Equipment | 7.64% | 66,369 | 5,070 | $ 58,989 |
| Contingencies | 20,812 | |||
| ----------- | ||||
| Total | $ 1,201,510 | |||
| Available Funds | ||||
| Proceeds of Bond Issue | $ 815,000 | |||
| Temporary Loan | 300,000 | |||
| State - site improvements | $ 82,000 | |||
| 5.5% 82,000 | 4,510 | 86,510 | ||
| $1,201,510 |