Board of Visitors minutes October 5, 2007 | ||
APPROVAL OF PROJECT BUDGET MODIFICATION
RESOLVED that after further study an increase to the Scott Stadium Waterproofing project of $2,343,000, bringing the total project budget to $4.7 million, is approved.
AGG:lah