Board of Visitors minutes April 11, 1996 | ||
5144
APPROVAL OF SCHEMATIC DESIGN FOR THE CONSTRUCTION OF
THE EMERGENCY OPERATIONS CENTER PROJECT
The following resolution was adopted:
- RESOLVED that the schematic design for the construction of the Emergency Operations Center Project as illustrated on drawings titled:
- 1. Site Plan (upper and lower level)
- 2. Floor Plans (upper and lower level)
- 3. Elevations (North, South, East, West) and Building Cross Section (Front to Back)
- dated March 11, 1996, and prepared by Hayes, Seay, Mattern & Mattern of Roanoke, Virginia, is approved;
- RESOLVED FURTHER that the project design shall be presented for review at the preliminary design level of development.
Board of Visitors minutes April 11, 1996 | ||